
|

Construction Timeline: (Floor)
Follow the progress of our new home construction. (7/22/2002 - 9/17/2002)
NOTE: Newest pictures at the top.
Click on any image for an enlargement.
Sep 17, 2002
The final pour commences. |

Despite getting up at the crack of dawn (for us) and driving for 3
1/2 hours to see the slab being poured, we arrived just as the
pumper was leaving. This is how the slab looked just after
being hand leveled.
|

We are using an acid etch and sealant on our floors to
provide an "Art" finish with excellent durability and
heat transfer, so the surface needs to be very smooth to begin
with. These "Power Screeds" are used to provide a
smooth surface.
|

While two guys work on keeping the edges smooth and flat, two
other guys manhandle the power-screeds over the surface. We
had glass fibers included in the concrete to resist cracking, so
the screeding process also helps to keep them below the surface.
|

Click on this image to get a close look at the final surface
quality. It's a far cry from the initial wet surface.
|

A quick photo-break before the "Welding Rod" crew
head off into the distance. They had two projects going
today, a foundation pour off Garrett Hwy, and our slab.
|

Here are the radiant heat pipes protruding from the
concrete. It's already hard to remember all those loops
below the floor. I noticed that the pressure gauge read zero when
I arrived. I hope that's OK :(
|

A final panorama from the back corner of the rear wall.
When we left the site at about 4:00pm, it was cool and overcast,
but the slab was HOT to the touch. I see what they mean
about concrete heating up as it cures.
|
|
Sep 11, 2002
The Radiant Heat pipes are laid.
So many clips, so little time :). |

The Knisely crew arrived right on time at 8:00am to start
installation of the PEX piping. Gary and Dan did all the hard
work.
|

Eric supervises the setup. A spool of pipe is placed in the
utility room where all the loops will terminate. Knisely has
a program that takes the room sizes and heat loads and determines
the pipe spacing.
|

The pipes are fixed in place with these COOL clips that screw into
the foam board. Then the tubing is just snapped into the
clips.
|

The guys snap chalk lines at the prescribed
spacing in each zone, and then the clips are inserted.
|

Each zone is fed by a series of loops. Each loop is 250'
long. This ensures that each loop gets a balanced flow of
water. The start and end of each loop is fed back to the
utility room.
|

The 4 zones are visible here. The garage (4) is the
rectangle to the far left, the guest zone (3) is the pie slice in the
center-left, and the Living zone (2) is in the center, and the
Master Zone (1) is to the right
|
|
Sep 9, 2002
Laying the slab insulation.
The slab is insulated from the ground using 2" of extruded
foam block.
This provides an insulation value of R10. |

First we laid down a roll of 16' wide vapor barrier. Then we
started in the back corner and started laying the 4'x8' sheets of
foam. We staggered the blocks on each row.
|

Holes were cut in the foam for pipes and forms.
Cutting was performed with a regular hand saw (wood), and a
keyhole saw that used a hack-saw blade. Having a relatively flat
gravel bed made laying the foam "sub-floor" pretty easy.
|

Lisa got into the act (after fixing some car troubles). Here
she is doing her "I can be macho too" act.
|

The blocks of foam were all joined together using Duct Tape.
Lisa joked that you could hear the hammers being used at the other
home sites, but at ours, all you could hear was duct tape ripping.
|
|
Aug 22, 2002
The floor begins by marking out the locations for plumbing rough-ins.
These photos are courtesy of Gary and Connie again. |

Here you can see that Gary has laid out some of the wall positions
(red lines) to enable him to mark the rough-ins for plumbing
drains etc (red circles). Gary has also marked the positions
for the concrete pads (red boxes) that will provide the structural
support for the upper level Gazebo. Also note that the
large piles of dirt in front of the house have been moved, and
used as backfill.
|

The plumbing contractor (Heilig's) has laid out the
sewer line run in white chalk. It leads down to the main
penetration in the 6" knee wall.
In addition to the feeders to the normal sewer line, we have 4
floor drains in the slab to deal with water run-off in the
sunroom, laundry, utility room and wheel-in guest shower. We
also need a conduit in the slab to bring power to the kitchen
island.
|
|
© 2000-2018, Phil and Lisa's relaxed lifestyle home.
An exercise in Energy Smart, Not So Big living.
www.OurCoolHouse.com - Ideas @ OurCoolHouse.com
|
|
This site is all about building a cool, energy efficient house,
that makes maximum use of earth sheltered design, passive solar heating and cooling,
geothermal exchange energy management, and right sizing of the house for it's designated use.
The home's placement is on a south-facing hillside in Deep Creek Lake, Maryland.
This site describes the design process, the technologies used and the expected results.
We also have a comprehensive Links Page for anyone who is also interested in designing a
similar project.
|