
|

Construction Timeline: (Foundation)
Follow the progress of our new home construction. (6/20/2002 - 7/7/2002)
NOTE: Newest pictures at the top.
Click on any image for an enlargement.
Aug 7, 2002
Stone base is in, ready for backfill & plumbing.
Lisa and I took a trip to visit the site, and also talk to the
HVAC guys about the system. This was the first time Lisa had seen
the house for real. |

Thanks to the magic of Photo-Stitch, Lisa is in this photo 3
times. Note the compacted gravel laid ready to accept the
slab. Click the image to see the three sides of Lisa.
|

Lisa and I pose for a Kodak Picture moment. It was a
beautiful 70° day. Lisa took a nap on the gravel for
few minutes.
|

Lisa's showing off the ferns growing wild in our back yard.
She kinda matches the scenery with that top she's wearing.
|

Here's a shot of the back corner. I've circled the line of
penetrations in the side wall. The pipes to the geothermal
wells will pass through these holes. We have an allowance
for 5 wells. I'm hoping that we can get by with only three
or four.
|

Lisa gives me the "evil-eye" through one of the 1 1/2
inch penetration holes
|
|
Aug 2, 2002
Walls are done.
No sooner are the forms up, then they need to be torn down
again. |

Here you see the West side retaining wall. It's 9' 8" tall,
with an overall length of 67 feet. Looking at these photos, I'm
glad we did a poured wall rather than Concrete block.
|

Here's the East side retaining wall. Both walls will have the
earth pushed back up against the full length, to form a protective
thermal barrier.
|
|
July 31, 2002
Now it's time to pour the walls.
Once the footings set up, the guys from "The Welding Rod"
returned and framed up the front and rear walls. Then they brought
in the pump truck and let rip with concrete. Gary took these pics
for me since it's a 3 hour trip for me each way. |

I never realized how much form work there was involved with
pouring concrete walls. The rear walls are 10" thick so
the wet concrete weighs a ton. The form also included a special
section with eleven 1 1/4" PVC pipe sections. These act
as penetrators for the Well water and Geothermal loop pipes.
|

I wish I'd been there to see the pumping operation. The
concrete mixer in the foreground is loading the pumper in the
background.
|
|
|
|
July 25, 2002
The Footings are laid.
Oh Boy... Now we're cooking. The house footprint had been
excavated, and the footer forms laid. This morning, before I
arrived, the footers were poured. It was So Cool to see my
design take shape. It was also neat to see some of the
technologies being used for this first step of the job. |

Here's a super wide shot of the footings taken from the East
corner of the house. The taller footings on the right are
the 2' wide base for the two rear retaining walls of the
house. These walls are mostly below grade, so the footings
are level with the bottom of the slab. The more complex
front footings are trenched lower to be below the frost
line. They will have a short 6" knee wall on top to
bring them up to the slab height. |

Here I am in the back corner, showing how far below grade this
point is. That post next to me is 8' long. Although
the soil currently tapers down as you move away from the back
corner, the earth will be back-filled to form a level earth berm
all the way along both of these walls |

Here's my builder, Gary Young. He's transferring a string line
to the concrete, ready for the next set of forms to be
placed. The rear walls will be 10" thick
concrete. Gary was reluctant to be photographed, assuring me
that Connie usually took care of that side of the business :) |
OK,
this is a Form-a-Drain. It's 8" tall and is used as a
form for the footings. The solid side is placed against the
concrete, and the slots face the crushed stone. The upper
chanel is used to collect Radon, and the lower channel collects
water. The picture on the right shows their placement on my
footings. |

Here you see the Form-a-Drain in action. Notice the slots on
the inside and outside of the footing. Also note the special
corners that join the drains together. The inner and outer drains
are joined with a bridge, and then the collected water is carried
away from the house with a main drain. Click the image for
more details
|
|
June 26, 2002
Ground clearing
is complete.
I spent an hour or so re-locating the back corner of the house and
correcting the South bearing. It turns out that a good old
magnetic compass is much more repeatable than my GPS with it's built-in
compass. I realized that something was up when I noticed that the
GPS unit pulled the magnetic compass off it's heading. D'oh! |
|
June 20, 2002
Ground clearing begins.
I hammered in two posts that we used as the center line for the
house. We then cleared an area around the house footprint plus a
20ft buffer zone. Many of the trees were new growth, and in danger
of falling on the house, so I was happy to see them go.. |

This is a very large panorama of the home site after the trees
were felled.
The view is down the hill to the South. |

We just got our main road paved so now the driveway needs to
be beefed up. Bring on that culvert and load of stone. |

Here are the crew that did the manual labor. Arland and
Joe. |

This back-hoe was used to clear the stumps and scrape the
building site smooth. |

When I went to lunch I noticed that you could see the smoke
from our burn pile. Now I know where our lot is :) |
|
© 2000-2018, Phil and Lisa's relaxed lifestyle home.
An exercise in Energy Smart, Not So Big living.
www.OurCoolHouse.com - Ideas @ OurCoolHouse.com
|
|
This site is all about building a cool, energy efficient house,
that makes maximum use of earth sheltered design, passive solar heating and cooling,
geothermal exchange energy management, and right sizing of the house for it's designated use.
The home's placement is on a south-facing hillside in Deep Creek Lake, Maryland.
This site describes the design process, the technologies used and the expected results.
We also have a comprehensive Links Page for anyone who is also interested in designing a
similar project.
|